Step by step New Traffic Bridge gets closer

Main Roads WA report that the continuing relocation of services at the Old Traffic Bridge pave the way for construction works on the New Bridge to begin. Here’s the latest update from Main Roads.

Services relocation

For decades, the old Fremantle Traffic Bridge has been home to several telecommunication and water service lines that require relocation to allow construction of the new bridge to begin.

Picture 1: Telecommunications drill rig on Beach Street

Telecommunications

Relocation of the telecommunication service line was completed last month. Seven new Telstra pipes were installed under the river, with the help of a horizontal directional drill rig. Telstra contractors are currently connecting the new service line to the existing network. Once complete, the old service lines on the bridge will be disconnected.

Steering a horizontal directional drill rig is complex and requires highly skilled operators. To steer a drill rig:
* Signal controllers are positioned on the northern and southern sides of the river.
* A line wire is continuously fed through the drill pipe to the drill tip and transmits a signal to the surface.
* The signal controllers then broadcast the signal from the drill tip and transmit its location to the steering crew.
* The steering crew can then adjust the angle of the drill tip to avoid any obstacles and stay on course.

A marker on the northern embankment showed where the drill needed to resurface. This photo shows the drill tip hit the marker right on target!

Picture 2: Telecommunications drill exit point

Water

Preparation is underway to relocate water services. There is a hive of activity on both sides of the river, preparing for the arrival of a new, larger drill rig.

Relocating water is complex. The pipes are:
Six times the size of the telecommunications pipe.

Approximately 400 metres long when segments are welded together.

Once filled with water, will weigh over 200 tonnes.

Pressure tested to ensure there are no leaks prior to installation.

The car park on Podger Lane (near the Swan Hotel) and the shared path adjacent to the rail line are closed to provide space to string, weld and pressure test two water pipes.

Picture 3: 630mm water pipe section (left) and 110mm telecommunications pipe section (right)

Upcoming works

Construction of site offices, ramps and temporary jetties.

Main Roads WA site office and associated facilities will be set up in North Fremantle near the Podger Lane car park. Site preparation works will be followed by construction of the ramps and temporary jetties, which will be done at the same time as water service relocation works, and once relevant approvals have been received. These works include:
* Vegetation removal on the north-east and north-west sides of the bridge.
* Excavation and foundation preparation works to build ramps for the temporary jetties (including drainage and pavement construction).
* Piling (on land and in river) to build the temporary jetties which will support the cranes used to construct the new bridge.
* Abutment concrete construction, including piling and earthworks.
* Temporary jetties will be used throughout construction and removed at project completion.

Picture 4: All four temporary jetties

Sharing the importance of Aboriginal heritage with the next generation

Since 2020, a Whadjuk Elders Advisory Group has provided valuable insight, which has informed the design of the project. Common themes heard over this time included:
*Reducing the number of pylons in the river to create an uninterrupted flow of the river water at the location of the crossings, along with the importance of traditional song lines.
* Ensuring a clear understanding of local history and cultural significance.

Last month, the project hosted a BBQ with Whadjuk Elder, Freda Ogilvie and a group of Aboriginal students from the Maali Mia Program at John Curtin College of the Arts.

The students will be working with Freda in coming months to design a project logo.

Picture 5: Left, Rory (Alliance Environmental Manager) with Freda Ogilvie

~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~

* If you’d like to COMMENT on this or any of our stories, don’t hesitate to email our Editor.

** WHILE YOU’RE HERE –

*** Don’t forget to SUBSCRIBE to receive your free copy of The Weekly Edition of the Shipping News each Friday!

****AND Shipees, here’s how to ORDER YOUR FSN MERCH. Fabulous Tees with great options now available!